EPS@ISEP | The European Project Semester (EPS) at ISEP


Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revisionPrevious revision
Next revision
Previous revision
plan [2019/03/11 15:16] – [Project Plan] team2plan [2019/06/19 11:54] (current) – [Gantt Chart] team2
Line 8: Line 8:
   * 2019-03-22 Upload the detailed **System Schematics & Structural Drawings** to the wiki and do the **cardboard scale model** of the structure   * 2019-03-22 Upload the detailed **System Schematics & Structural Drawings** to the wiki and do the **cardboard scale model** of the structure
   * 2019-03-27 Upload the **List of Materials (what & quantity)** to the wiki   * 2019-03-27 Upload the **List of Materials (what & quantity)** to the wiki
-  * 2019-04-06 Upload the **Interim Report and Presentation** to the wiki. The report must contain the the following chapters: Introduction, Project Management, State of the Art, Marketing Plan, Project Management, Eco-eficiency Measures for Sustainability, Ethical and Deontological Concerns, Proposed Solution and Bibliography. The Project Management chapter includes the updated project progress register, the sprint report for completed sprints (tasks that were included, statuses, assignees, allocations) and the updated release Gantt chart +  * 2019-04-06 Upload the **Interim Report and Presentation** to the wiki. The report must contain the the following chapters: Introduction, Project Management, State of the Art, Marketing Plan, Eco-efficiency Measures for Sustainability, Ethical and Deontological Concerns, Proposed Solution and Bibliography. In particular, the Project Management chapter includes the updated project progress register, the sprint report for completed sprints (tasks that were included, statuses, assignees, allocations) and the updated release Gantt chart 
   * 2019-04-11 Interim Presentation, Discussion and Peer, Teacher and Supervisor Feedbacks   * 2019-04-11 Interim Presentation, Discussion and Peer, Teacher and Supervisor Feedbacks
   * 2019-04-23 Complete the **List of Materials (local providers & price, including VAT and transportation)** to the wiki   * 2019-04-23 Complete the **List of Materials (local providers & price, including VAT and transportation)** to the wiki
Line 35: Line 35:
 <WRAP box 400px center> <WRAP box 400px center>
 ^ Sprint    ^ Start          ^ Finish     ^ ^ Sprint    ^ Start          ^ Finish     ^
-| 1         | 04.03.2019     | 10.03.2019 |    +| 1         | 18.02.2019     | 24.02.2019 |    
-| 2         | 11.03.2019     | 17.03.2019 |      +| 2         | 25.03.2019     | 03.03.2019 |      
-| 3         | 18.03.2019     | 24.03.2019 | +| 3         | 04.03.2019     | 13.03.2019 | 
-| 4         | 25.03.2019     | 31.03.2019 | +| 4         | 14.03.2019     | 20.03.2019 | 
-| 5         | 01.04.2019     | 07.04.2019 |   +| 5         | 21.03.2019     | 27.04.2019 |   
-| 6         | 08.04.2019     | 15.04.2019 | +| 6         | 28.03.2019     | 03.04.2019 | 
-| Easter Holidays| -              | -          | +| 7         | 04.04.2019     | 10.04.2019 |    
-| 7         | 22.04.2019     | 28.04.2019 |    +| 8         | 11.04.2019     | 24.04.2019 |      
-| 8         | 29.04.2019     | 05.05.2019 |      +^  Easter Holiday  ^^^ 
-| Students Week| -              | -          | +| 9         | 25.04.2019     | 02.05.2019 | 
-| 9         | 13.05.2019     | 19.05.2019 | +^  Students Week  ^^^ 
-| 10        | 20.05.2019     | 26.05.2019 | +| 10        | 03.05.2019     | 16.05.2019 | 
-| 11        | 27.05.2019     | 02.06.2019 | +| 11        | 17.05.2019     | 23.05.2019 | 
-| 12        | 03.06.2019     | 09.06.2019 | +| 12        | 24.05.2019     | 30.05.2019 | 
-| 13        | 10.06.2019     | 16.06.2019 |+| 13        | 31.05.2019     | 06.06.2019 | 
 +| 14        | 07.06.2019     | 13.06.2019 | 
 +| 15        | 14.06.2019     | 20.06.2019 | 
 +| 16        | 21.06.2019     | 28.06.2019 |
 </WRAP> </WRAP>
 </table> </table>
Line 64: Line 67:
 | Z         | Explore EU directives / Food regulations   | Done     |    | Z         | Explore EU directives / Food regulations   | Done     |   
 | X         | Sponge Experiment    | Done            |  | X         | Sponge Experiment    | Done            | 
-| A         | Principle Research   | In Progress     | +| A         | Principle Research   | Done     | 
-| B         | Competition Analysis | In Progress     | +| B         | Competition Analysis | Done     | 
-| C         | Features Research    | In Progress     | +| C         | Features Research    | Done      | 
-| D         | Air Flow techniques  | In Progress     |    +| D         | Air Flow techniques  | Done      |    
-| E         | Condensation Solution Research    | In Progress       |+| E         | Condensation Solution Research    | Done        |
 | F         | "Black Box" System Diagrams   | Done   | | F         | "Black Box" System Diagrams   | Done   |
-| G         | Initial Structural Draft | In Progress |    +| G         | Initial Structural Draft | Done  |    
-| H         | Presentation Chapther- Report    | In Progress |  +| H         | Presentation Chapther- Report    | Done  |  
-| I         | Motivation Chapther - Report   | In Progress   | +| I         | Motivation Chapther - Report   | Done    | 
-| J         | Ideas for Functional Tests Chapter - Report | not done |    +| J         | Ideas for Functional Tests Chapter - Report | Done |    
-| K         | Technical Research, Literature Review     | To do      |    +| K         | Technical Research, Literature Review     | Done       |    
-| L         | Market Research, Existing products    | To do      |    +| L         | Market Research, Existing products    | Done       |    
-| M         | Business Plan   | To do      |    +| M         | Business Plan   | Done      |    
-| N         | Material/Resource analysis/Selection  | To do      |      +| N         | Material/Resource analysis/Selection  | Done       |      
-| O         | Initial Budget Planning   | To do      |    +| O         | Initial Budget Planning & List of Materials  | Done       |    
-| P         | Interim Presentation   | To do      |    +| P         | Interim Presentation   | Done     |    
-| Q         | Interim Report   | To do      |      +| Q         | Interim Report   | Done |      
-| R         | Design Developement  | To do      |        +| R         | Design Developement  | Done      |        
-| S         | Construction Hardware   | To do      |    +| S         | Construction Hardware   | Done      |    
-| T         | Material buying  | To do      |      +| T         | Material buying  | Done      |      
-| U         | Assembly   | To do      | +| U         | Assembly   | Done      | 
-| V         | Process Testing   | To do      |    +| V         | Process Testing   | Done     |    
-| W         | Functional Tests  | To do      |      +| W         | Functional Tests  | Done      |      
-| AB         | Design change implimentation    | To do      | +| AB         | Design change implimentation    | Done      | 
-| AC        | Report   | To do      |    +| AC        | Report   | Done      |    
-| AD         | Video   | To do      |      +| AD         | Video   | Done      |      
-| AE         | Poster  | To do      | +| AE         | Poster  | Done      | 
-| AF         | Presentation   | To do      | +| AF         | Presentation   | Done      | 
-| AG         | Manual   | To do      |+| AG         | Manual   | Done      |
 </WRAP> </WRAP>
 </table> </table>
Line 126: Line 129:
 <WRAP box 400px center> <WRAP box 400px center>
 ^ Sprint    ^ PBI   ^ Responsible  ^ Involved   ^ Status      ^ ^ Sprint    ^ PBI   ^ Responsible  ^ Involved   ^ Status      ^
-| 1         | Y     | All Team     | All Team   | Done        | +| 1 | Y | All Team | All Team   | Done        | 
-| 1         | Z     | Elisa        |            | Done        |   +| 1 | Z | Elisa |   | Done |   
-| 1         | X     | João         |            | Done        |+| 1 | X | João |  | Done | 
 +| 3 | B | Joao & Nacho | All Team | Done | 
 +| 3 | C | Pascal & Elisa |  | Done | 
 +| 3 | D | Joao |  | Done |  
 +| 3 | E | Pascal | Daniel | Done | 
 +| 3 | F | Pascal & Elisa |  | Done | 
 +| 3 | G | Marie     |  | Done | 
 +| 4 | A | Marie & Daniel |   | Done | 
 +| 4 | H | Marie   |    | Done | 
 +| 4 | I | Pascal  |    | Done | 
 +| 4 | J | Daniel  |    | Done | 
 </WRAP> </WRAP>
 </table> </table>
 </WRAP> </WRAP>
  
-Identify key project deliverables (when they will be started and completed) and build a release **Gantt chart**.+===== Gantt Chart ===== 
 + 
 +[[report#time|Report, Project Management, Gantt Chart]] 
 + 
 +===== Sprint Outcomes ===== 
 + 
 +[[report#sprint_outcomes|Report, Project Management, Sprint Outcomes]]
  
 +===== Sprint Evaluations =====
  
-  * 1st week plan: {{ :gantt_chart_1st_week.png?linkonly |}} ; {{ :gantt_chart_1st_week.xlsx |}} +[[report#sprint_evaluations|Report, Project Management, Sprint Evaluations]]
-  * 2nd week plan: {{ :gantt_chart_2nd_week.png?linkonly |}}+
QR Code
QR Code plan (generated for current page)