plan [2019/03/11 15:02] – [Project Plan] team2plan [2019/06/19 11:54] (current) – [Gantt Chart] team2
Line 8: Line 8:
   * 2019-03-22 Upload the detailed **System Schematics & Structural Drawings** to the wiki and do the **cardboard scale model** of the structure   * 2019-03-22 Upload the detailed **System Schematics & Structural Drawings** to the wiki and do the **cardboard scale model** of the structure
   * 2019-03-27 Upload the **List of Materials (what & quantity)** to the wiki   * 2019-03-27 Upload the **List of Materials (what & quantity)** to the wiki
-  * 2019-04-06 Upload the **Interim Report and Presentation** to the wiki. The report must contain the the following chapters: Introduction, Project Management, State of the Art, Marketing Plan, Project Management, Eco-eficiency Measures for Sustainability, Ethical and Deontological Concerns, Proposed Solution and Bibliography. The Project Management chapter includes the updated project progress register, the sprint report for completed sprints (tasks that were included, statuses, assignees, allocations) and the updated release Gantt chart +  * 2019-04-06 Upload the **Interim Report and Presentation** to the wiki. The report must contain the the following chapters: Introduction, Project Management, State of the Art, Marketing Plan, Eco-efficiency Measures for Sustainability, Ethical and Deontological Concerns, Proposed Solution and Bibliography. In particular, the Project Management chapter includes the updated project progress register, the sprint report for completed sprints (tasks that were included, statuses, assignees, allocations) and the updated release Gantt chart 
   * 2019-04-11 Interim Presentation, Discussion and Peer, Teacher and Supervisor Feedbacks   * 2019-04-11 Interim Presentation, Discussion and Peer, Teacher and Supervisor Feedbacks
   * 2019-04-23 Complete the **List of Materials (local providers & price, including VAT and transportation)** to the wiki   * 2019-04-23 Complete the **List of Materials (local providers & price, including VAT and transportation)** to the wiki
Line 35: Line 35:
 <WRAP box 400px center> <WRAP box 400px center>
 ^ Sprint    ^ Start          ^ Finish     ^ ^ Sprint    ^ Start          ^ Finish     ^
-| 1         | 04.03.2019     | 10.03.2019 |    +| 1         | 18.02.2019     | 24.02.2019 |    
-| 2         | 11.03.2019     | 17.03.2019 |      +| 2         | 25.03.2019     | 03.03.2019 |      
-| 3         | 18.03.2019     | 24.03.2019 | +| 3         | 04.03.2019     | 13.03.2019 | 
-| 4         | 25.03.2019     | 31.03.2019 | +| 4         | 14.03.2019     | 20.03.2019 | 
-| 5         | 01.04.2019     | 07.04.2019 |   +| 5         | 21.03.2019     | 27.04.2019 |   
-| 6         | 08.04.2019     | 15.04.2019 | +| 6         | 28.03.2019     | 03.04.2019 | 
-| Easter Holidays| -              | -          | +| 7         | 04.04.2019     | 10.04.2019 |    
-| 7         | 22.04.2019     | 28.04.2019 |    +| 8         | 11.04.2019     | 24.04.2019 |      
-| 8         | 29.04.2019     | 05.05.2019 |      +^  Easter Holiday  ^^^ 
-| Students Week| -              | -          | +| 9         | 25.04.2019     | 02.05.2019 | 
-| 9         | 13.05.2019     | 19.05.2019 | +^  Students Week  ^^^ 
-| 10        | 20.05.2019     | 26.05.2019 | +| 10        | 03.05.2019     | 16.05.2019 | 
-| 11        | 27.05.2019     | 02.06.2019 | +| 11        | 17.05.2019     | 23.05.2019 | 
-| 12        | 03.06.2019     | 09.06.2019 | +| 12        | 24.05.2019     | 30.05.2019 | 
-| 13        | 10.06.2019     | 16.06.2019 |+| 13        | 31.05.2019     | 06.06.2019 | 
 +| 14        | 07.06.2019     | 13.06.2019 | 
 +| 15        | 14.06.2019     | 20.06.2019 | 
 +| 16        | 21.06.2019     | 28.06.2019 |
 </WRAP> </WRAP>
 </table> </table>
Line 63: Line 66:
 | Y         | Comunication Plan    | Done            | | Y         | Comunication Plan    | Done            |
 | Z         | Explore EU directives / Food regulations   | Done     |    | Z         | Explore EU directives / Food regulations   | Done     |   
-| K         | Sponge Experiment    | Done            |  +| X         | Sponge Experiment    | Done            |  
-| Y         | Principle Research   | In Progress     | +| A         | Principle Research   | Done     | 
-| Z         | Air Flow techniques  | In Progress     |    +| B         | Competition Analysis | Done     | 
-| K         | Condensation Solution Research    | In Progress       | +| C         | Features Research    | Done      | 
-| Y         | "Black Box" System Diagrams   | Done   | +| D         | Air Flow techniques  | Done      |    
-| Z         | Initial Structural Draft | In Progress |    +| E         | Condensation Solution Research    | Done        | 
-| K         | Presentation Chapther- Report    | In Progress |  +| F         | "Black Box" System Diagrams   | Done   | 
-| Y         | Motivation Chapther - Report   | In Progress   | +| G         | Initial Structural Draft | Done  |    
-| Z         | Ideas for Functional Tests Chapter - Report | not done |    +| H         | Presentation Chapther- Report    | Done  |  
-| D         | Technical Research, Literature Review     | To do      |    +| I         | Motivation Chapther - Report   | Done    | 
-| A         | Market Research, Existing products    | To do      |    +| J         | Ideas for Functional Tests Chapter - Report | Done |    
-| B         | Business Plan   | To do      |    +| K         | Technical Research, Literature Review     | Done       |    
-| C         | Material/Resource analysis/Selection  | To do      |      +| L         | Market Research, Existing products    | Done       |    
-| T         | Initial Budget Planning   | To do      |    +| M         | Business Plan   | Done      |    
-| R         | Interim Presentation   | To do      |    +| N         | Material/Resource analysis/Selection  | Done       |      
-| U         | Interim Report   | To do      |      +| O         | Initial Budget Planning & List of Materials  | Done       |    
-| O         | Design Developement  | To do      |        +| P         | Interim Presentation   | Done     |    
-| L         | Construction Hardware   | To do      |    +| Q         | Interim Report   | Done |      
-| P         | Material buying  | To do      |      +| R         | Design Developement  | Done      |        
-| S         | Assembly   | To do      | +| S         | Construction Hardware   | Done      |    
-| F         | Process Testing   | To do      |    +| T         | Material buying  | Done      |      
-| V         | Functional Tests  | To do      |      +| U         | Assembly   | Done      | 
-| N         | Design change implimentation    | To do      | +| V         | Process Testing   | Done     |    
-| H         | Report   | To do      |    +| W         | Functional Tests  | Done      |      
-| M         | Video   | To do      |      +| AB         | Design change implimentation    | Done      | 
-| Q         | Poster  | To do      | +| AC        | Report   | Done      |    
-| W         | Presentation   | To do      | +| AD         | Video   | Done      |      
-| I         | Manual   | To do      |+| AE         | Poster  | Done      | 
 +| AF         | Presentation   | Done      | 
 +| AG         | Manual   | Done      |
 </WRAP> </WRAP>
 </table> </table>
Line 103: Line 108:
 | 1         | Y     | 4             | All Team     | All Team   | | 1         | Y     | 4             | All Team     | All Team   |
 | 1         | Z     | 7             | Elisa        |            |      | 1         | Z     | 7             | Elisa        |            |     
-| 1         | K     | 2             | João         |            | +| 1         | X     | 2             | João         |            | 
-| 2         |       | 7             | Marie & Dániel    |       | +| 2         | A     | 7             | Marie & Dániel    |       | 
-| 2         |       | 7             | João & Ignacio    |       |      +| 2         | B     | 7             | João & Ignacio    |       |      
-| 2         |       | 7             | Pascal & Elisa    |       | +| 2         | C     | 7             | Pascal & Elisa    |       | 
-| 2         |       | 7             | João         |            | +| 2         | D     | 7             | João         |            | 
-| 2         |       | 7             | Dániel & Pascal   |       |      +| 2         | E     | 7             | Dániel & Pascal   |       |      
-| 2         |       | 1             | Elisa & Pascal    |       | +| 2         | F     | 1             | Elisa & Pascal    |       | 
-| 2         |       | 1             | Marie        |            | +| 2         | G     | 1             | Marie        |            | 
-| 2         |       | 3             | Marie        |            |      +| 2         | H     | 3             | Marie        |            |      
-| 2         |       | 3             | Pascal       |            | +| 2         | I     | 3             | Pascal       |            | 
-| 2         |       | 3             | Dániel       |            |+| 2         | J     | 3             | Dániel       |            |
 </WRAP> </WRAP>
 </table> </table>
Line 124: Line 129:
 <WRAP box 400px center> <WRAP box 400px center>
 ^ Sprint    ^ PBI   ^ Responsible  ^ Involved   ^ Status      ^ ^ Sprint    ^ PBI   ^ Responsible  ^ Involved   ^ Status      ^
-| 1         | Y     | All Team     | All Team   | Done        | +| 1 | Y | All Team | All Team   | Done        | 
-| 1         | Z     | Elisa        |            | Done        |   +| 1 | Z | Elisa |   | Done |   
-| 1         | K     | João         |            | Done        |+| 1 | X | João |  | Done | 
 +| 3 | B | Joao & Nacho | All Team | Done | 
 +| 3 | C | Pascal & Elisa |  | Done | 
 +| 3 | D | Joao |  | Done |  
 +| 3 | E | Pascal | Daniel | Done | 
 +| 3 | F | Pascal & Elisa |  | Done | 
 +| 3 | G | Marie     |  | Done | 
 +| 4 | A | Marie & Daniel |   | Done | 
 +| 4 | H | Marie   |    | Done | 
 +| 4 | I | Pascal  |    | Done | 
 +| 4 | J | Daniel  |    | Done | 
 </WRAP> </WRAP>
 </table> </table>
 </WRAP> </WRAP>
  
-Identify key project deliverables (when they will be started and completed) and build a release **Gantt chart**.+===== Gantt Chart ===== 
 + 
 +[[report#time|Report, Project Management, Gantt Chart]] 
 + 
 +===== Sprint Outcomes =====
  
 +[[report#sprint_outcomes|Report, Project Management, Sprint Outcomes]]
  
-  * 1st week plan: {{ :gantt_chart_1st_week.png?linkonly |}} ; {{ :gantt_chart_1st_week.xlsx |}} +===== Sprint Evaluations =====
-  * 2nd week plan: {{:gantt_chart_2ndweek.png?linkonly|}}+
  
 +[[report#sprint_evaluations|Report, Project Management, Sprint Evaluations]]